Today we received our Certificate of Occupancy for the wet slips. Slip holders will be putting their vessels on the dock in the coming days and weeks. There is a docking diagram in the Harbormaster’s office.
The Morgan River Outpost restaurant is doing some décor work and equipment modifications. Their licensing should arrive by the beginning of February which is when they plan to open for dinner service.
We had a major wheel failure on the forklift making it inoperable. Parts are needed as is work at a machine shop. We apologize for the inconvenience and project that the repair will take between 7 and 10 days.
We expect to resume fueling operations in two weeks after some final approval from the Department of Health and Environmental Control. Ethanol free gas and diesel will be available.
Work is progressing and we look forward to being fully permitted soon!